友情提示:如果本网页打开太慢或显示不完整,请尝试鼠标右键“刷新”本网页!阅读过程发现任何错误请告诉我们,谢谢!! 报告错误
飞读中文网 返回本书目录 我的书架 我的书签 TXT全本下载 进入书吧 加入书签

the life of thomas telford-第75章

按键盘上方向键 ← 或 → 可快速上下翻页,按键盘上的 Enter 键可回到本书目录页,按键盘上方向键 ↑ 可回到本页顶部!
————未阅读完?加入书签已便下次继续阅读!




principal contractors for mason work on the Caledonian Canal。

The building operations were begun with great vigour early in 1820。

The three arches on the Caernarvonshire side and the four on the

Anglesea side were first proceeded with。  They are of immense

magnitude; and occupied four years in construction; having been

finished late in the autumn of 1824。  These piers are 65 feet in

height from high…water line to the springing of the arches; the

span of each being 52 feet 6 inches。  The work of the main piers

also made satisfactory progress; and the masonry proceeded so

rapidly that stones could scarcely be got from the quarries in

sufficient quantity to keep the builders at work。  By the end of

June about three hundred men were employed。



The two principal piers; each 153 feet in height; upon which the

main chains of the bridge were to be suspended; were built with

great care and under rigorous inspection。  In these; as indeed in

most of the masonry of the bridge; Mr。 Telford adopted the same

practice which he had employed in his previous bridge structures;

that of leaving large void spaces; commencing above high water mark

and continuing them up perpendicularly nearly to the level of the

roadway。  〃I have elsewhere expressed my conviction;〃 he says; when

referring to the mode of constructing these piers; 〃that one of the

most important improvements which I have been able to introduce

into masonry consists in the preference of cross…walls to rubble;

in the structure of a pier; or any other edifice requiring strength。

Every stone and joint in such walls is open to inspection in the

progress of the work; and even afterwards; if necessary; but a

solid filling of rubble conceals itself; and may be little better

than a heap of rubbish confined by side walls。〃  The walls of these

main piers were built from within as well as from without all the

way up; and the inside was as carefully and closely cemented with

mortar as the external face。  Thus the whole pier was bound firmly

together; and the utmost strength given; while the weight of the

superstructure upon the lower parts of the work was reduced to its

minimum。



'Image' Section of Main Pier



Over the main piers; the small arches intended for the roadways

were constructed; each being 15 feet to the springing of the arch;

and 9 feet wide。  Upon these arches the masonry was carried

upwards; in a tapering form; to a height of 53 feet above the

level of the road。  As these piers were to carry the immense weight

of the suspension chains; great pains were taken with their

construction; and all the stones; from top to bottom; were firmly

bound together with iron dowels to prevent the possibility of their

being separated or bulged by the immense pressure they had to

withstand。



The most important point in the execution of the details of the

bridge; where the engineer had no past experience to guide him; was

in the designing and fixing of the wrought iron work。  Mr。 Telford

had continued his experiments as to the tenacity of bar iron; until

he had obtained several hundred distinct tests; and at length;

after the most mature delilberation; the patterns and dimensions

were finally arranged by him; and the contract for the manufacture

of the whole was let to Mr。 Hazeldean; of Shrewsbury; in the year

1820。  The iron was to be of the best Shropshire; drawn at Upton

forge; and finished and proved at the works; under the inspection

of a person appointed by the engineer。



'Image' Cut showing fixing of the chains in the rock



The mode by which the land ends of these enormous suspension chains

were rooted to the solid ground on either side of the Strait; was

remarkably ingenious and effective。  Three oblique tunnels were made

by blasting the rock on the Anglesea side; they were each about six

feet in diameter; the excavations being carried down an inclined

plane to the depth of about twenty yards。  A considerable width of

rock lay between each tunnel; but at the bottom they were all

united by a connecting horizontal avenue or cavern; sufficiently

capacious to enable the workmen to fix the strong iron frames;

composed principally of thick flat cast iron plates; which were

engrafted deeply into the rock; and strongly bound together by the

iron work passing along the horizontal avenue; so that; if the iron

held; the chains could only yield by tearing up the whole mass of

solid rock under which they were thus firmly bound。



A similar method of anchoring the main chains was adopted on the

Caernarvonshire side。  A thick bank of earth had there to be cut

through; and a solid mass of masonry built in its place; the rock

being situated at a greater distance from the main pier; involving

a greater length of suspending chain; and a disproportion in the

catenary or chord line on that side of the bridge。  The excavation

and masonry thereby rendered necessary proved a work of vast

labour; and its execution occupied a considerable time; but by the

beginning of the year 1825 the suspension pyramids; the land piers

and arches; and the rock tunnels; had all been completed; and the

main chains were firmly secured in them; the work being

sufficiently advanced to enable the suspending of the chains to be

proceeded with。  This was by far the most difficult and anxious part

of the undertaking。



With the same careful forethought and provision for every

contingency which had distinguished the engineer's procedure in the

course of the work; he had made frequent experiments to ascertain

the actual power which would be required to raise the main chains

to their proper curvature。  A valley lay convenient for the purpose;

a little to the west of the bridge on the Anglesea side。

Fifty…seven of the intended vertical suspending rods; each nearly

ten feet long and an inch square; having been fastened together; a

piece of chain was attached to one end to make the chord line 570

feet in length; and experiments having been made and comparisons

drawn; Mr。 Telford ascertained that the absolute weight of one of

the main chains of the bridge between the points of suspension was

23 1/2 tons; requiring a strain of 39 1/2 tons to raise it to its

proper curvature。  On this calculation the necessary apparatus

required for the hoisting was prepared。  The mode of action finally

determined on for lifting the main chains; and fixing them into

their places; was to build the central portion of each upon a raft

450 feet long and 6 feet wide; then to float it to the site of the

bridge; and lift it into its place by capstans and proper tackle。



At length all was ready for hoisting the first great chain; and

about the middle of April; 1825; Mr。 Telford left London for Bangor

to superintend the operations。  An immense assemblage collected to

witness the sight; greater in number than any that had been

collected in the same place since the men of Anglesea; in their

war…paint; rushing down to the beach; had shrie
返回目录 上一页 下一页 回到顶部 0 0
未阅读完?加入书签已便下次继续阅读!
温馨提示: 温看小说的同时发表评论,说出自己的看法和其它小伙伴们分享也不错哦!发表书评还可以获得积分和经验奖励,认真写原创书评 被采纳为精评可以获得大量金币、积分和经验奖励哦!